You may have noticed a few more contractors' vehicles on site this week and as predicted it has been a very busy week on site in general. It's great to see the window installation and exterior claddings well underway and the “first fix" for the services (wiring, pipework and duct-work) almost completed. We just need to complete the membrane on the lower roof this week and it will be a good week all around.

The next week we will be another busy one completing the window installation, installing the insulation to the walls and lower ceiling, lining some of the ceilings and walls inside, completing the roofing membrane, installing flashings, starting the weather boards, continuing the exterior cladding around the main church area and hopefully start some drainage in the car park outside.

The Intregra panels on the exterior of the main church are an interesting form of cladding, it is a very thick, stable and robust light stone like product which will end up looking great once plastered because of its stable and "flat" nature. Let's hope the rain stays away soon so we can have a fair go at plastering and painting it!

If you have any further queries please contact me 

Regards
Lance Strawbridge (Project Manager) 027 495 3722