Building Update- Hawkins Herald #8- 12nd November

posted Nov 11, 2014, 10:00 AM by Aidan Collett   [ updated Nov 11, 2014, 10:01 AM by Parishes of The Holy Family ]
As you can see the Church is starting to look closed in and hopefully by the end of next week we will be able to keep the interior dry so the insulation can start. The lower roof is now the key to achieving this which we are busy working on now.

We have also poured the floor slab infill inside the church and the entry slab. The entry slab has been poured with a black oxide in it which gives it a dark colour, this slab is also an exposed aggregate slab which makes it an attractive non-slip area.

Next week will be a very busy week with all the services trades starting on site to install their wiring, ducting and pipe work. We will also be installing the windows on the exterior, the water-proof membrane to the roof and starting the exterior cladding. This is the key week for the project because of all the critical tasks and the amount of work planned for the week. A prayer or two on Sunday for some fine weather would be appreciated!

If you have any further queries please contact me :) 

The entry slab and has been poured and the building is closing in fast

 
Regards 
Lance Strawbridge (Project Manager) 0274953722 