Building Update- Hawkins Herald #12- 5th December

posted Dec 6, 2014, 8:54 PM by Aidan Collett   [ updated Dec 6, 2014, 8:54 PM by Parishes of The Holy Family ]
As you can image it has been another busy week on site, we have had all the trades there working on completing their tasks. This week's efforts has set us up well for completing the main church area next week. This obviously takes a lot of co-ordination so Straun and our site team have been doing a great job keeping the flow of works smooth for everyone.

Next week is the big one, the services will be completed in most areas, the glazing will be complete, the ceiling tiles will be installed, the floor coverings will be laid, the painting will be complete in the main church area, the floor will be polished in the entry and the landscaping/ site works will be well underway.

I have to congratulate the church and the Architect Darrell Bell for the design of the LED light windows and the church in general. I guarantee everyone will be amazed at the window glazing design and it was great to hear about the story behind them, the passion and commitment for the project from the parishioners is refreshing and certainly helps the team during this busy time on site so thanks to everyone involved!

If you have any further queries please contact me :)

Regards
Lance Strawbridge (Project Manager) 027 495 3722