The breakdown of the New Church expenses:
Hawkins Contract $1,089,958
Airconditioning $75,000
Variance costs $24,329
Carpark/sitework $160,000
Total paid to Hawkins $1,349,287

Additional Costs:
Stained Glass $126,000
Sound System etc $75,103
Pew refurbishment $38,550
Consultants, Fees $92,122
Demolition $81,179
Total Costs= $1,756,241

Total Funds Raised to date $1,656,241
Sum Paid    $1,756,241

Shortfall Borrowed from Diocese to be repaid by 01/03/2016        $100,000